Storage at the logistics site—for self-consumption of solar power and peak loads
At Fiege’s logistics facility in Greven, a Voltfang battery storage system increases the PV system’s self-consumption and reduces peak loads. Voltfang is implementing the project as the general contractor in two phases: Phase 1 with 2.5 MWh; expansion to 5 MWh is planned by 2027.
Capacity
5 MWh
Power
2.4 MW
Storage duration
2 h
Grid connection
Medium voltage
Location
Greven, North Rhine-Westphalia
Project Overview
- Location: Greven, North Rhine-Westphalia
- Grid connection: Medium voltage (10 kV), existing grid connection at the site
- Voltfang’s role: General contractor for the storage facility
- Usage: Optimization of self-consumption, peak load shaving, electricity trading
- Expansion: Phase 1 starting in Q4 2025 (2.5 MWh), Phase 2 by 2027 (5 MWh)
One storage system, three tasks
At Fiege, the large-scale battery storage system balances out volatile generation and fluctuating demand: It optimizes the self-consumption of PV systems and is used for arbitrage trading and the sale of flexibility. In the future, it will also buffer the high charging power required for electric trucks, thereby smoothing out peak loads.
Voltfang's Scope of Services
1
Implementation (Full EPC)
One-stop planning and implementation of the project
2
Battery Systems
Delivery of Voltfang Battery Storage Systems
3
Technical Operations
Voltfang will serve as the technical operator of the BESS
“
The collaboration and actual project implementation with Voltfang went really well and was actually a lot of fun.