AWA Entsorgung – Electrification of the Warden Waste Management Center

At the Warden Waste Management Center in Eschweiler (NRW), trucks, excavators, and wheel loaders are increasingly running on electricity—charged with up to 400 kW from onsite solar and landfill gas power. Energy costs fall by up to 82% per year, bringing AWA significantly closer to its climate targets. This is made possible by a battery storage system from Voltfang that intelligently coordinates generation, charging infrastructure, and consumers.

Company

“We have been generating our own electricity on site for years. Thanks to the storage system, we can deploy it precisely as needed—exactly when our plant, vehicles, and machinery require it.”
– Maren Killewald, Managing Director, AWA Entsorgung GmbH

The project in figures

up to 82%
lower annual energy costs thanks to PV, CHP, and storage
up to 400 kW
charging capacity for electric trucks and heavy electric equipment
540 kWh
Total storage capacity on site
270 kW
Total storage output on site

One battery storage system, four tasks

Voltfang designed a storage system for Warden that covers four use cases simultaneously. Everything is managed via the Voltfang energy management system (EMS), which controls generation, charging infrastructure, and consumers in a unified system.

The diagram shows how energy flows across the site depending on the task the storage system is currently performing: peak shaving, bridging CHP outages, supporting charging infrastructure, and optimizing self-consumption.

Photovoltaics
CHP
Power grid
Battery storage540 kWh · 270 kW
Charging infrastructure
Buildings & facilities
Peak shaving

Absorb load peaks and reduce strain on the grid connection. The battery covers charging peaks so the connected load does not have to scale to peak demand.

Bridging CHP outages

Short-term compensation during outages or maintenance of the landfill gas CHP plant. The site remains powered without drawing unexpected power from the grid.

Supporting charging infrastructure

Providing additional capacity for charging vehicles—up to 400 kW is available on site, including for heavy commercial vehicles.

Self-consumption optimization

Utilizing generated PV electricity for buildings, the leachate treatment plant, and the increasingly electrified fleet and machinery.

Modular construction – keeping pace with electrification

The site started with a single storage unit and was gradually expanded to three units with a combined capacity of 540 kWh and 270 kW output. Each expansion phase followed the actual progress of the vehicle fleet.

The advantage for operational depots: the storage system grows with the fleet. Investments are made step by step according to actual demand—instead of upfront spending on a system that will only reach full capacity years later. This keeps the site flexible for future expansion stages as well.

Our energy storage solution

Capacity

540 kWh

Performance

270 kW

Additional reference projects

More projects where Voltfang implemented battery storage systems for commercial, industrial, and municipal clients—from logistics and steel trading to EV charging hubs.

How we proceed

Contact request & consulting
Once you have requested an appointment, you will receive an assessment of potential, financing options and a profitability analysis in a free consultation.
Contact request & consulting
Once you have requested an appointment, you will receive an assessment of potential, financing options and a profitability analysis in a free consultation.
Technical data query
After the consultation, the available site information is also recorded for preliminary review.
Technical data query
After the consultation, the available site information is also recorded for preliminary review.
Offer or project planning order
Depending on the data available, we can prepare a quote for your battery storage project directly or collect any missing information together on site.
Offer or project planning order
Depending on the data available, we can prepare a quote for your battery storage project directly or collect any missing information together on site.
On-site appointment and project planning
Inspection of the site for your battery storage project by a Voltfang engineer & project planning.
On-site appointment and project planning
Inspection of the site for your battery storage project by a Voltfang engineer & project planning.
Order
Review & approval of the offer.
Order
Review & approval of the offer.
Obtaining permits
Voltfang takes care of the necessary registrations and applications (grid operator, building application, etc.).
Obtaining permits
Voltfang takes care of the necessary registrations and applications (grid operator, building application, etc.).
Offer or project planning order
Voltfang is centrally responsible for all project steps and trades so that you only have one central point of contact.
Offer or project planning order
Voltfang is centrally responsible for all project steps and trades so that you only have one central point of contact.
Comprehensive services in operation
Voltfang provides continuous support after installation. Our team is always available for questions and support to guarantee optimum system functions.
Comprehensive services in operation
Voltfang provides continuous support after installation. Our team is always available for questions and support to guarantee optimum system functions.